Driving strong productivity outcomes at Ipswich Hospital Expansion
Ipswich Hospital Expansion being delivered by BESIX Watpac is tracking on time and budget.

Strong productivity outcomes are shaped by decisions made early in a project's lifecycle and carried through every stage of delivery.
At the Ipswich Hospital Expansion, the team assessed a range of construction methodologies before selecting an integrated jump form system that offered significant time and cost benefits over alternative approaches.
The methodology enables core walls to be poured every 11 days, compared with around 25 days using other methods. The result is a significant productivity boost that is helping keep the program moving.
The project team also worked closely with partners to develop an innovative approach to the construction of the precast stair towers, allowing them to be constructed ahead of the main structure using crawler cranes.
The results speak for themselves, with the structure now reaching Level 10, façade installation progressing to Level 7 and fit-out works underway to Level 7.
Together, these initiatives highlight the value of careful planning, collaboration and selecting the right construction methodology for the job.

BESIX Watpac brings Victorian project partners together for an industry update
Sharing market insights, strengthening relationships and exploring what it takes to build high-performing teams with Joel Selwood.

BESIX Watpac tops the nation at the AIB Awards
A remarkable month of industry recognition for BESIX Watpac has culminated in national honours at the Australian Institute of Building (AIB) Professional Excellence Awards.

Creating pathways for women in construction
Fifteen women are set to launch their careers in construction after graduating from the Ignite HER Pathway Program at Bank Street Park, a project being delivered by BESIX Watpac.